CARLTON AT HAMILTON MILL
  • Home
  • Make a Payment
  • Property Management
  • New Homeowners
  • LEARN ABOUT CARLTON
    • HOA FINANCIALS
    • Important Documents
    • Realtors
    • LEASING
    • FAQ
  • Amenities
    • Tennis Courts
    • Pool Season 2026
  • RESERVE FUNDED PROJECTS
    • ROOFING PROJECT (PHASE 1)
    • RETAINING WALL PROJECT (PHASE 1)
    • PAVING PROJECT (SARDIS CHASE LOOP)
  • Mailboxes
  • Contact
  • Text Alerts



PHASE 1 RETAINING WALL PROJECT UPDATE: February 25, 2025

Dear Residents,

We’re pleased to share that Wall 14 and Wall 15 are now complete.

Upcoming work is as follows:
  • Wall #10 – Construction will begin next week on around March 2nd (located behind 3300, 3302, 3304, 3306, and 3308 Sardis Bend).
    Please note that this will be the most complex wall completed so far in this project. As a result, nearby homeowners should expect a higher level of construction activity and temporary impact during the work.

  • Wall #11 – Scheduled for completion later this spring, prior to the opening of the pool.
  • See attached below map for Wall #10 and Wall #11 locations

IMPORTANT INFORMATION FOR WALL #10 
  • Utilities will be marked before work begins.
  • Privacy divider fencing will be removed during construction and replaced upon completion.
  • Impacted residents are encouraged to move patio items as they deem necessary.
  • RazorSharp will access exterior water spigots during construction and cleanup. A reminder that water costs are paid for by the Association 

We appreciate your patience and understanding as we complete these significant improvements to the community.

For any questions, please contact Access directly: [email protected]

Warm regards,

The Carlton at Hamilton Mill Board of Directors
Picture

PHASE 1 RETAINING WALL PROJECT UPDATE : January 6, 2026

Dear Carlton Residents,

We are pleased to share an update on the Phase 1 retaining wall replacement project.

Wall 15 has been fully completed, and work on Wall 14 will begin today. Construction on Wall 14 is expected to take approximately 1–2 weeks, weather permitting. A map of both walls can be found below. 
As a reminder, portions of fencing may need to be temporarily removed to accommodate the work. All fencing will be reinstalled once construction is complete.

During certain phases of the project, Razor Sharp may access exterior water spigots on nearby homes. The contractor will use their own hoses and equipment, and all affected areas will be protected.
The Board is very pleased with the quality of work completed thus far and is confident this project will be a significant improvement to our community.
Thank you for your continued patience and cooperation as we complete this important work.

If you have questions or concerns, please contact the Board directly: [email protected]

--
The Board of Directors
Carlton at Hamilton Mill





SPECIAL ANNOUNCEMENT!
UPCOMING PHASE 1 RETAINING WALL PROJECT TO BEGIN NOVEMBER 17th 

 


Dear Carlton Residents,

We wanted to make you aware of an upcoming Retaining Wall Replacement Project – Phase 1, which will focus on Walls 14 and 15 (see attached map for reference).

Project Overview
Following a competitive bidding process, the Board selected Razor Sharp Lawn & Landscape to complete this important project. The work will include the removal and replacement of the existing retaining walls, grading, and new sod installation once complete.


Tentative Start Date: Week of November 17, 2025 (weather permitting)
Contractor: Razor Sharp Lawn & Landscape
Estimated Duration: Approximately 1–2 weeks per wall


Project Schedule
Wall 15 will be completed first, beginning the week of November 17.
Wall 14 will be completed shortly thereafter in December, weather permitting.

What to Expect
Heavy equipment such as a compact loader/skid steer and mini-excavator will be onsite for timber and gravel movement.
Safety cones will mark the active work zone, and vehicles/equipment may be staged near one or both ends of Wall 15 during construction.
Pedestrian and vehicle access will remain open throughout the project.
The contractor will keep the area neat and safe at the end of each workday.

We appreciate your patience and cooperation as we complete this important infrastructure improvement. Please use extra caution when walking or driving near the project area during this time.

If you have questions or concerns, please contact the Board directly: [email protected]

Warm regards,
The Carlton at Hamilton Mill Board of Directors



Picture

TEXT alerts


We now offer community text alerts!

Click here to sign up

Location

Contact Us

  • Home
  • Make a Payment
  • Property Management
  • New Homeowners
  • LEARN ABOUT CARLTON
    • HOA FINANCIALS
    • Important Documents
    • Realtors
    • LEASING
    • FAQ
  • Amenities
    • Tennis Courts
    • Pool Season 2026
  • RESERVE FUNDED PROJECTS
    • ROOFING PROJECT (PHASE 1)
    • RETAINING WALL PROJECT (PHASE 1)
    • PAVING PROJECT (SARDIS CHASE LOOP)
  • Mailboxes
  • Contact
  • Text Alerts