🚧 Carlton Paving Project Update – Thursday April 16th 

🎉 Exciting News — Paving is COMPLETE! 🎉


Final finishing touches and punch list items will be completed today (Thursday) and tomorrow (Friday).

🚗 Access Update
One lane will remain open at all times
Residents may resume normal access throughout the day

🚧 What to Expect Over the Next Two Days
Parking pad will be painted and striped
New speed bumps will be installed and painted
(Please note: these will be a gentler, less pronounced design)
Gate sensors are being installed and calibrated
Gates will return to normal operation very soon

Final Notes from the Board
The Board would like to extend a sincere thank you to our paving vendor for their coordination and hard work throughout this project. This project would not have been possible without the support and cooperation of so many good-hearted residents in our community who have been kind, understanding, and even helpful to us along the way. As a reminder, the Board is made up of just three volunteer members, and we have dedicated countless hours planning and coordinating to make this project as seamless and successful as possible.

We are proud of the result—this new asphalt will be enjoyed for years to come, enhances the overall appearance of the neighborhood, and contributes positively to our home values. Carlton truly looks like a brand-new community.

Looking ahead, we have plans to pave Sardis Bend Drive in 2027, with more details to come in the future.

Thank you again for your patience, cooperation, and support!







🚧 Carlton Paving Project Update – Wednesday Afternoon April 15th 

🕘 IMPORTANT: Paving will be completed today, and ALL residents may return to their driveways beginning at 9:00 PM tonight.
🚫 Do NOT attempt to drive on Sardis Chase Court before 9:00 PM.

⚠️ Midday Update
Around 3:00 PM today, there was a brief issue at the front entrance gate—the most complex portion of the project—where both the entrance and exit lanes were temporarily closed due to a logistical issue. The paving team acted quickly and had a lane reopened within approximately 25 minutes.
Aside from this brief window, emergency vehicle access has been maintained at all times throughout the project.

🚫 Critical Reminders
Do NOT stop your vehicle to move cones or barricades
Do NOT drive through any blocked-off areas
Avoid driving OR walking on milled or newly paved asphalt
Parents: please ensure children stay clear of all work zones

🚗 Parking Reminders (Until 9:00 PM)
Park along designated curb areas on Sardis Bend Drive (inner loop)
Use the clubhouse/pool parking lot
Park ONLY in designated areas to allow emergency access
Do NOT block driveways or fire hydrants

📅 What’s Next
Tonight (April 15): Roads reopen at 9:00 PM
April 16: Final striping and finishing work (minimal impact; normal access resumes for all residents)

Final Notes from the Board
The Board would like to extend a sincere thank you to our paving vendor for their coordination and hard work throughout this project. This project would not have been possible without the support and cooperation of so many good-hearted residents in our community who have been kind, understanding, and even helpful to us along the way. As a reminder, the Board is made up of just three volunteer members, and we have dedicated countless hours planning and coordinating to make this project as seamless and successful as possible.

We are proud of the result—this new asphalt will be enjoyed for years to come, enhances the overall appearance of the neighborhood, and contributes positively to our home values. Carlton truly looks like a brand-new community.

Looking ahead, we have plans to pave Sardis Bend Drive in 2027, with more details to come in the future.

Thank you again for your patience, cooperation, and support!








🚧 Carlton Paving Project Update – Wednesday Morning April 15th 

Thank you to the many residents who have shown patience and compliance during this project. We’ve observed several homeowners walking to and from their vehicles, and we truly appreciate your cooperation.

However, we are also aware that a number of residents have ignored directives, including moving barricades and driving on freshly laid asphalt. These actions compromise the project and create safety concerns. Violators will be subject to fines and enforcement.

We are in the final stretch—thank you for bearing with us!

🕘 Paving will be completed today, and roads will reopen at 9:00 PM.
🚫 DO NOT stop your vehicle to move cones or barricades
🚫 DO NOT drive through any blocked-off areas

Thank you for helping us bring this project to a successful completion.




🚧 Carlton Paving Project Update – Tuesday April 14th 


Please stay on sidewalks at all times and avoid walking on milled or newly paved asphalt.

Parents, please remind children to do the same for their safety.

🚫 Barricades are in place for a reason—please obey all barricades.
🚫 Do NOT move barricades or drive on the Sardis Chase Court loop during construction.


 You will not be able to return home with your vehicle until Wednesday April 15 at 9pm. 

Thank you for your cooperation in keeping everyone safe and protecting this project.


Parking will be available:
• Along designated curb parking areas along inner loop of Sardis Bend Drive
• At the clubhouse/pool parking area

Vehicles must be parked only in designated areas marked in
RED on the project map (see below and attached) to ensure emergency vehicle access, along the inner loop of Sardis Bend closest to the clubhouse/tennis courts overflow lot.
Should parking become limited, residents may consider adjacent parking areas nearest the community as options.
 
Do not block driveways or fire hydrants.
 
The overflow parking lot nearest the front gate will be closed beginning April 13 at 8am through April 16 for striping.
 
Traffic control personnel will be present during milling and paving operations to assist with traffic flow.
 
Front gates will remain in the open position April 13–16 for construction access.
 
SPECIAL SAFETY NOTICE
 
Construction machinery, work zones, and materials present safety hazards and should be avoided at all times.
 
Emergency vehicles will always have access to at least one open lane throughout the project.
 
 

KEY DATES & CRITICAL INFORMATION
 
April 15 (Phase 2)
Asphalt paving continues 
Residents may return vehicles to Sardis Chase Court Loop and resume street/driveway access beginning at 9pm
 
April 16 (Phase 2)
Final striping and finishing touches work continues with minimal impact to residents. Residents may come and go as they normally would.
 
STAY INFORMED
 
Daily updates will be provided for the duration of the Phase 2 project.

 
For daily updates, it is imperative that residents sign up for community text alerts and follow the community Facebook page.
 
Text Alerts
https://platform.mobile-text-alerts.com/subscribe/CarltonHM
 
Community Facebook Page
https://www.facebook.com/groups/1380191702009235
 
 
Thank you in advance for your cooperation and patience as we complete these important improvements to our Carlton at Hamilton Mill community.


See below for downloadable Community Map (jpeg)
Park only in the designated areas in red on the map (inner loop of Sardis Bend Drive, clubhouse/pool parking lot)
Do not block driveways or fire hydrant


Picture




🚧 Carlton Paving Project Update – Monday evening update
April 13th 


PHASE 2
ASPHALT REPAVING PROJECT
Location: Sardis Chase Court
Impacted Residents: All residents who reside on the Sardis Chase Court loop, to include Sardis Bend (3300, 3301, 3302, 3303, 3304, 3305, 3306, 3308) 
 
Dates: April 14 – April 16, 2026
 
April 14: Asphalt milling (removal of old pavement) and asphalt paving 
April 15: Asphalt paving
April 16: Striping of the small overflow lot near the front gate
 
The milling machine will arrive and be staged on April 13 on the cul-de-sac across from 2632 Sardis Chase Court. The paving machine will arrive the morning of April 14.
 
During Phase 2, ALL residents who reside at the addresses notated above must move their vehicles to the Sardis Bend Drive section of the community no later than April 14th at 8am. You will not be able to return home with your vehicle until Wednesday April 15 at 9pm. 
 
Parking will be available:
• Along designated curb parking areas along inner loop of Sardis Bend Drive
• At the clubhouse/pool parking area

Vehicles must be parked only in designated areas marked in
RED on the project map (see below and attached) to ensure emergency vehicle access, along the inner loop of Sardis Bend closest to the clubhouse/tennis courts overflow lot.
Should parking become limited, residents may consider adjacent parking areas nearest the community as options.
 
Do not block driveways or fire hydrants.
 
The overflow parking lot nearest the front gate will be closed beginning April 13 at 8am through April 16 for striping.
 
Traffic control personnel will be present during milling and paving operations to assist with traffic flow.
 
Front gates will remain in the open position April 13–16 for construction access.
 
SPECIAL SAFETY NOTICE
 
Parents are asked to speak with children about the dangers associated with construction activity.
 
Construction machinery, work zones, and materials present safety hazards and should be avoided at all times.
 
Emergency vehicles will always have access to at least one open lane throughout the project.
 
 

KEY DATES & CRITICAL INFORMATION

April 14 (Phase 2)
Road milling  and paving begins
All Sardis Chase Court vehicles must be relocated by 8:00 AM April 14.
 
April 15 (Phase 2)
Asphalt paving continues 
Residents may return vehicles to Sardis Chase Court Loop and resume street/driveway access beginning at 9pm
 
April 16 (Phase 2)
Final striping and finishing touches work continues with minimal impact to residents. Residents may come and go as they normally would.
 
STAY INFORMED
 
Daily updates will be provided for the duration of the Phase 2 project.

 
For daily updates, it is imperative that residents sign up for community text alerts and follow the community Facebook page.
 
Text Alerts
https://platform.mobile-text-alerts.com/subscribe/CarltonHM
 
Community Facebook Page
https://www.facebook.com/groups/1380191702009235
 
 
Thank you in advance for your cooperation and patience as we complete these important improvements to our Carlton at Hamilton Mill community.




CARLTON AT HAMILTON MILL
COMMUNITY ANNOUNCEMENT

 
SARDIS CHASE COURT LOOP PAVING PROJECT
PHASE 1: CURB & SIDEWALK REPAIR (NOW COMPLETED!)
PHASE 2: ASPHALT REPAVING

 
BACKGROUND
 
The Carlton at Hamilton Mill community was originally developed beginning in 2005. The Sardis Chase Court loop represents the oldest section of the community, with the Sardis Bend Drive section being completed several years later after 2008.
 
Since the community’s construction, no major repairs or maintenance have been completed on the curbs, sidewalks, or asphalt roads. As a result, many areas have reached the point where repair and replacement are necessary to maintain the safety, functionality, and appearance of our neighborhood.
 
The Board has identified curb sections showing the most deterioration and sidewalks requiring leveling as priorities for repair. In addition, the asphalt roads on Sardis Chase Court are well beyond the stage where seal coating would be effective and now require full repaving.
 
Major infrastructure improvements inevitably cause temporary inconvenience for residents. While the HOA will do everything possible to minimize disruption, the success of this project will depend on cooperation and patience from the community. The end result will be a safer, more attractive neighborhood for everyone. The Sardis Chase Court Loop Paving project will be completed over a total of two phases, Phase 1 and Phase 2.
 
Please note that similar paving priorities are planned for the Sardis Bend Drive section of the community in 2027. Additional information will be provided closer to that time.

PHASE 2
ASPHALT REPAVING PROJECT
Location: Sardis Chase Court
Impacted Residents: All residents who reside on the Sardis Chase Court loop, to include Sardis Bend (3300, 3301, 3302, 3303, 3304, 3305, 3306, 3308)
 
Dates: April 14 – April 16, 2026
 
April 14: Asphalt milling (removal of old pavement) and asphalt paving 
April 15: Asphalt paving
April 16: Striping of the small overflow lot near the front gate
 
The milling machine will arrive and be staged on April 13 on the cul-de-sac across from 2632 Sardis Chase Court. The paving machine will arrive the morning of April 14.
 
During Phase 2, ALL residents who reside at the addresses notated above must move their vehicles to the Sardis Bend Drive section of the community no later than April 14th at 8am. You will not be able to return home with your vehicle until Wednesday April 15 at 9pm. 
 
Parking will be available:
• Along designated curb parking areas along inner loop of Sardis Bend Drive
• At the clubhouse/pool parking area

Vehicles must be parked only in designated areas marked in
RED on the project map (see below and attached) to ensure emergency vehicle access, along the inner loop of Sardis Bend closest to the clubhouse/tennis courts overflow lot.
Should parking become limited, residents may consider adjacent parking areas nearest the community as options.
 
Do not block driveways or fire hydrants.
 
The overflow parking lot nearest the front gate will be closed beginning April 13 at 8am through April 16 for striping.
 
Traffic control personnel will be present during milling and paving operations to assist with traffic flow.
 
Front gates will remain in the open position April 13–16 for construction access.
 
Weather conditions may require schedule adjustments.
 
SPECIAL SAFETY NOTICE
 
Parents are asked to speak with children about the dangers associated with construction activity.
 
Construction machinery, work zones, and materials present safety hazards and should be avoided at all times.
 
Emergency vehicles will always have access to at least one open lane throughout the project.
 
 

KEY DATES & CRITICAL INFORMATION

April 13 (Phase 2)
Construction equipment staging begins
Overflow lot nearest the front gate will close and must be entirely vacated of all vehicles by 8:00 AM
 
April 14 (Phase 2)
Road milling  and paving begins
All Sardis Chase Court vehicles must be relocated by 8:00 AM April 14.
 
April 15 (Phase 2)
Asphalt paving continues 
Residents may return vehicles to Sardis Chase Court Loop and resume street/driveway access beginning at 9pm
 
April 16 (Phase 2)
Final striping and finishing touches work continues with minimal impact to residents. Residents may come and go as they normally would.
 
STAY INFORMED
 
This letter serves as the primary official notice for this project.
 
For daily updates, it is imperative that residents sign up for community text alerts and follow the community Facebook page.
 
Text Alerts
https://platform.mobile-text-alerts.com/subscribe/CarltonHM
 
Community Facebook Page
https://www.facebook.com/groups/1380191702009235
 
 
Thank you in advance for your cooperation and patience as we complete these important improvements to our Carlton at Hamilton Mill community.










🚧 Carlton Paving Project Update – Monday April 6th 

Great news! Our concrete vendor has confirmed that the concrete has cured ahead of schedule.
All cones and caution tape have now been removed, and residents have full access to their driveways again.
We want to sincerely thank the many residents who followed guidelines and helped protect this important community project. Your cooperation made a big difference in allowing the work to be completed successfully.

🚧 Looking Ahead:
The next phase of the project will begin April 14, which will again impact access along Sardis Chase.
Additional details and reminders will be shared as we approach that date.
Thank you again for your cooperation and support!





🚧 Carlton Paving Project Update – Thursday, April 2nd 

The project continues to run smoothly—thank you all for your outstanding cooperation!

Concrete pouring is now complete, and the curing phase is underway. Do not enter or disturb any taped or coned-off areas to allow proper curing and prevent damage.


Impacted residents:
Please plan to return to your driveways no sooner than Tuesday, April 7 at 5:00 PM. We will confirm once access is officially restored.

Reminders:
🚫 No street parking (strictly prohibited)
🚗 Please continue to park at:
• Upper parking pad near the entrance gate
• Clubhouse/pool parking lot

👨‍👩‍👧 Parents, please continue to ensure children stay clear of construction areas.

📅 Update Schedule:
Due to the Easter holiday, daily updates will pause Friday through Sunday. Updates will resume on Monday, April 6.

Thank you again for your patience and cooperation—you’ve made this process smooth and successful for everyone!





🚧 Carlton Paving Project Update – Wednesday, April 1st

Thank you to everyone for your cooperation today — it has been exceptional. We’re happy to report the project began smoothly with zero issues, and all impacted residents successfully moved their vehicles. We truly appreciate the community’s support.

Reminder:
🚫 You may not return to your driveway today 
Driveways will be inaccessible for approximately 6 days (exact return date TBD and will be communicated).

🚧 Impacted driveways will be clearly marked with tape and cones.
Please do not tamper with these barriers or park in these areas until further notice.

👨‍👩‍👧 Parents, please remind children to stay clear of construction areas for their safety.

Thank you again for your patience and cooperation as we complete this important project.



🚧 Carlton Paving Project Update – Tuesday, March 31

Reminder to all impacted homes (18 units with blocked driveways):

2620 Sardis Chase Court
2732 Sardis Chase Court
2709 Sardis Chase Court
2622 Sardis Chase Court
2730 Sardis Chase Court
2697 Sardis Chase Court
2624 Sardis Chase Court
2728 Sardis Chase Court
2645 Sardis Chase Court
2626 Sardis Chase Court
2726 Sardis Chase Court
2651 Sardis Chase Court
2628 Sardis Chase Court
2724 Sardis Chase Court
2434 Sardis Chase Court
2630 Sardis Chase Court
2722 Sardis Chase Court
2632 Sardis Chase Court


To prevent potential delays, please move your vehicles to overflow parking this evening (Tuesday, March 31)
🚨 All vehicles MUST be moved no later than 8:00 AM tomorrow (Wednesday, April 1)
Vehicles left in driveways after this time will be blocked in for approximately 6 days.


🚗 Parking Instructions:
• No street parking
• Use upper parking pad by entrance gate or clubhouse/pool parking


We will provide updates on when driveway access can resume as the project progresses.
Daily updates will be provided for the duration of the Phase 1 project.

Thank you for your cooperation and support!

CARLTON AT HAMILTON MILL
COMMUNITY ANNOUNCEMENT

 
SARDIS CHASE COURT LOOP PAVING PROJECT
PHASE 1: CURB & SIDEWALK REPAIR
PHASE 2: ASPHALT REPAVING

 
BACKGROUND
 
The Carlton at Hamilton Mill community was originally developed beginning in 2005. The Sardis Chase Court loop represents the oldest section of the community, with the Sardis Bend Drive section being completed several years later after 2008.
 
Since the community’s construction, no major repairs or maintenance have been completed on the curbs, sidewalks, or asphalt roads. As a result, many areas have reached the point where repair and replacement are necessary to maintain the safety, functionality, and appearance of our neighborhood.
 
The Board has identified curb sections showing the most deterioration and sidewalks requiring leveling as priorities for repair. In addition, the asphalt roads on Sardis Chase Court are well beyond the stage where sealcoating would be effective and now require full repaving.
 
Major infrastructure improvements inevitably cause temporary inconvenience for residents. While the HOA will do everything possible to minimize disruption, the success of this project will depend on cooperation and patience from the community. The end result will be a safer, more attractive neighborhood for everyone. The Sardis Chase Court Loop Paving project will be completed over a total of two phases, Phase 1 and Phase 2.
 
Please note that similar paving priorities are planned for the Sardis Bend Drive section of the community in 2027. Additional information will be provided closer to that time.
 
 PHASE 1
CONCRETE CURB & SIDEWALK REPAIR
Location: Sardis Chase Court
Impacted Residents: Please see list of addresses below
 
Dates: April 1 and April 2, 2026
 
April 1: Removal of damaged curb and sidewalk material
April 2: Pouring of new concrete for repairs
 
Concrete requires approximately 5–6 days to fully cure. There will be noise generated by the project.
 
Residents should look for areas marked with white paint near curbs and sidewalks indicating where repairs will occur.
 
Some repairs will require full driveway access to be temporarily blocked while the concrete cures. The following homes will be directly impacted:
 
2620 Sardis Chase Court
2732 Sardis Chase Court
2709 Sardis Chase Court
2622 Sardis Chase Court
2730 Sardis Chase Court
2697 Sardis Chase Court
2624 Sardis Chase Court
2728 Sardis Chase Court
2645 Sardis Chase Court
2626 Sardis Chase Court
2726 Sardis Chase Court
2651 Sardis Chase Court
2628 Sardis Chase Court
2724 Sardis Chase Court
2434 Sardis Chase Court
2630 Sardis Chase Court
2722 Sardis Chase Court
2632 Sardis Chase Court
 
 
Residents at the addresses listed above MUST move vehicles out of their driveways by 8:00 AM on April 1.
If your address is NOT listed above, you may continue to use your driveway normally during Phase 1.
 
To avoid delays, residents are strongly encouraged to move vehicles the evening before (Tuesday March 31st)
 
Failure to move vehicles by the deadline will result in residents being blocked in their driveway for the duration of the project (approximately 5–6 days).
 
During this time, affected residents must park in clubhouse/pool parking lot or the overflow lot nearest the entrance gate. Street parking is prohibited.
 
Construction will begin at 8:00 AM on both April 1 and April 2 and may continue until approximately 7:00 PM.
 
Front gates will remain in the open position during construction to allow contractor vehicle access.
 
Construction zones will be marked with reflective pylons and safety tape.
 
Weather conditions may require schedule adjustments.
 
PHASE 2
ASPHALT REPAVING PROJECT
Location: Sardis Chase Court
Impacted Residents: All residents who reside on the Sardis Chase Court loop, to include Sardis Bend (3300, 3301, 3302, 3303, 3304, 3305, 3306, 3308)
 
Dates: April 14 – April 16, 2026
 
April 14: Asphalt milling (removal of old pavement)
April 15: Asphalt paving
April 16: Striping of the small overflow lot near the front gate
 
The milling machine will arrive and be staged on April 13 on the cul-de-sac across from 2632 Sardis Chase Court. The paving machine will arrive the morning of April 15.
 
During Phase 2, ALL residents listed above must move their vehicles to the Sardis Bend Drive section of the community no later than April 14th at 8am. You will not be able to return home with your vehicle until Wednesday April 15 at 9pm. Attempting to drive on the milling or asphalt during this time frame not only compromises the project but may cause damage to your vehicle.
 
Parking will be available:
• Along designated curb parking areas on Sardis Bend Drive
• At the clubhouse/pool parking area
 
Vehicles must be parked only in designated areas marked in
RED on the project map (see below and attached) to ensure emergency vehicle access, along the inner loop of Sardis Bend closest to the clubhouse/tennis courts overflow lot. Should parking become limited, residents may consider adjacent parking areas nearest the community as options.
 
Do not block driveways or fire hydrants.
 
The overflow parking lot nearest the front gate will be closed from April 13 through April 16 for striping.
 
Traffic control personnel will be present during milling and paving operations to assist with traffic flow.
 
Front gates will remain in the open position April 13–16 for construction access.
 
Weather conditions may require schedule adjustments.
 
SPECIAL SAFETY NOTICE
 
Parents are asked to speak with children about the dangers associated with construction activity.
 
Construction machinery, work zones, and materials present safety hazards and should be avoided at all times.
 
Emergency vehicles will always have access to at least one open lane throughout the project.
 
 

KEY DATES & CRITICAL INFORMATION
 
March 31 (Phase 1)
Residents impacted by driveway concrete repairs (see list) are encouraged to move vehicles out of driveways in the evening to prevent delays the following morning.  
 
April 1 – April 2 (Phase 1)
Concrete curb and sidewalk repairs begin.
All vehicles that reside at affected addresses MUST be moved no later than 8am on Wednesday April 1st.
Driveways to affected homes will be inaccessible for approximately 5–6 days.
 
April 13 (Phase 2)
Construction equipment staging begins
Overflow lot nearest the front gate will close and must be entirely vacated of all vehicles
 
April 14 (Phase 2)
Road milling begins
All Sardis Chase Court vehicles must be relocated by 8:00 AM April 14.
 
April 15 (Phase 2)
Asphalt paving begins
Residents may return vehicles to Sardis Chase Court Loop and resume street/driveway access beginning at 9pm
 
April 16 (Phase 2)
Final striping and finishing touches work continues with minimal impact to residents. Residents may come and go as they normally would.
 
STAY INFORMED
 
This letter serves as the primary official notice for this project.
 
For daily updates, it is imperative that residents sign up for community text alerts and follow the community Facebook page.
 
Text Alerts
https://platform.mobile-text-alerts.com/subscribe/CarltonHM
 
Community Facebook Page
https://www.facebook.com/groups/1380191702009235
 
 
Thank you in advance for your cooperation and patience as we complete these important improvements to our Carlton at Hamilton Mill community.





TEXT alerts


We now offer community text alerts!

Click here to sign up

Location

Contact Us

  • Home
  • Make a Payment
  • Property Management
  • New Homeowners
  • LEARN ABOUT CARLTON
    • HOA FINANCIALS
    • Important Documents
    • Realtors
    • LEASING
    • FAQ
  • Amenities
    • Tennis Courts
    • Pool Season 2026
  • RESERVE FUNDED PROJECTS
    • ROOFING PROJECT (PHASE 1)
    • RETAINING WALL PROJECT (PHASE 1)
    • PAVING PROJECT (SARDIS CHASE LOOP)
  • Mailboxes
  • Contact
  • Text Alerts